How to Plan Your Home Renovation: Step-by-Step Timeline

How to Plan Your Home Renovation 1

RENOVATION TIMELINE QUICK REFERENCE

Project TypePlanning PhaseConstruction PhaseTotal TimelineKey Variables
Bathroom Remodel4-8 weeks3-10 weeks2-4 monthsFixture availability, plumbing complexity
Kitchen Remodel8-12 weeks6-12 weeks4-6 monthsCustom cabinets lead time, appliance delivery
Whole Home Renovation12-24 weeks16-24 weeks7-12 monthsPermit delays, living situation, scope changes
Master Suite Addition12-16 weeks12-20 weeks6-9 monthsFoundation work, weather, HVAC integration
Basement Finishing6-10 weeks4-8 weeks3-5 monthsMoisture issues, egress windows, code compliance
Cosmetic Updates2-4 weeks1-3 weeks1-2 monthsPaint drying time, material availability

Buffer Recommendation: Add 15-20% to all timeline estimates | Best Planning Start: 6-12 months before desired construction start

What Is a Home Renovation Timeline and Why Does It Matter?

A home renovation timeline is a detailed schedule that maps every phase of your project from initial planning through final completion, including specific start and end dates for design, permits, demolition, construction, and finishing work. Planning your timeline properly matters because renovation phases must occur in strict sequence you can’t install flooring before plumbing is approved, or hang cabinets before walls are painted. A realistic timeline coordinates multiple contractors, manages material lead times, accounts for inspection delays, and prevents costly downtime. Most renovation failures stem from unrealistic timelines that ignore dependencies, underestimate phases, or fail to buffer for inevitable delays.

Understanding what a renovation timeline actually encompasses is your first step toward realistic planning. This isn’t simply marking a start date and hoped-for completion date on your calendar. A proper timeline breaks your renovation into distinct phases, each with its own duration, dependencies, and critical milestones.

Your timeline serves as the coordination backbone for your entire project. Every contractor, supplier, inspector, and decision point gets plotted on this schedule. When your electrician asks when to start rough-in work, your timeline provides the answer. When you need to order kitchen cabinets, your timeline tells you the perfect moment—not so early that you’re paying storage fees, not so late that installation delays by weeks.

The timeline also protects your budget. Every delay costs money through extended contractor fees, additional temporary housing, or rush charges for materials you need immediately. A well-planned timeline with realistic durations and proper buffers prevents most delays from becoming budget disasters. For a comprehensive understanding of renovation costs and budgeting strategies, review our complete home renovation guide.

Perhaps most importantly, your timeline manages expectations for everyone involved. Your family knows when they’ll regain access to the kitchen. Your contractor knows when different trades need to mobilize. Suppliers understand delivery windows. When everyone operates from the same timeline, miscommunication and frustration decrease dramatically.

Phase 1: Pre-Planning Timeline (6-12 Months Before Construction)

Starting your timeline planning six to twelve months before you want construction to begin might seem excessive, but this pre-planning phase determines your project’s ultimate success. During these months, you’re not swinging hammers—you’re making the critical decisions and arrangements that prevent problems once construction starts.

Your first two months should focus on defining your project scope and establishing your budget. What exactly do you want to renovate? Which problems are you solving? What’s your must-have versus nice-to-have list? These decisions directly impact how long your project will take. A kitchen refresh with new appliances and paint takes weeks. A kitchen gut requiring all new plumbing, electrical, and custom cabinets takes months. Our detailed guide on renovation planning walks through this decision-making process systematically.

Months three through five involve selecting and hiring your design and construction teams. If you’re working with an architect or interior designer, their design phase alone can consume two to four months depending on project complexity and how quickly you provide decisions and feedback. Finding the right contractor requires interviewing multiple candidates, checking references, reviewing portfolios, and negotiating contracts. This process cannot be rushed without risking quality problems later.

During months six through eight, your designer finalizes plans and your contractor creates detailed construction schedules. This is when you’ll discover realistic duration estimates for each construction phase. Your contractor should provide a comprehensive timeline showing when each trade starts and finishes, material ordering windows, inspection points, and expected completion dates. Compare this contractor-provided timeline against your desired dates. If there’s a mismatch, adjust your expectations now, not after construction begins.

The final months before construction involve permit applications, material selections, and logistical preparations. Permit approval can take anywhere from two weeks to three months depending on your municipality and project complexity. While waiting for permits, finalize all material selections—flooring, tile, fixtures, appliances, cabinetry, countertops, paint colors. Order long-lead items like custom cabinets immediately after permit approval to prevent construction delays waiting for materials.

Use this pre-planning period to arrange temporary living situations if needed. Will you remain in your home during construction? If renovating your kitchen, can you create a temporary kitchen elsewhere? If gutting multiple bathrooms, do you have access to at least one functioning bathroom? If your renovation makes staying home impractical, book temporary housing now before better options disappear.

Phase 2: Design and Permitting Timeline (6-16 Weeks)

The design and permitting phase runs concurrently with your late pre-planning period but deserves special attention because these activities frequently cause unexpected delays. Understanding realistic timelines for design work and permit approval prevents frustration and keeps your overall schedule on track.

Design work duration depends entirely on project complexity and how many revision rounds occur. A simple bathroom update with standard fixtures might require just two weeks of design work. A whole-home renovation with custom elements, structural changes, and complex spatial reconfigurations can easily consume twelve to sixteen weeks of design time. Your designer creates initial concepts, you provide feedback, they revise, you review again—this cycle continues until you approve final plans.

You accelerate design timelines by providing prompt, decisive feedback. When your designer sends concepts for review, respond within two to three days with clear preferences and concerns. Vague feedback like “I don’t love it” forces designers to guess what you want, leading to more revision cycles. Specific feedback like “I prefer the galley kitchen layout but want the island from option two” gives clear direction that speeds the process.

Once design finalizes, permit applications begin. Your contractor or architect typically handles permit submissions, but understanding the process helps you plan realistically. Most municipalities require detailed construction drawings, structural calculations for any bearing wall modifications, electrical and plumbing plans, and energy compliance calculations. Preparing these documents takes one to two weeks after design approval.

Permit review and approval timelines vary wildly by location. Some small municipalities approve simple projects within two weeks. Large cities with backlogged building departments can take eight to twelve weeks for complex renovations. Call your local building department early in planning to ask about current permit processing times. Add two weeks to whatever timeframe they quote—permit delays are common.

Some renovations require additional approvals beyond standard building permits. Historic district renovations need historic commission approval. Significant exterior changes may require architectural review board approval. Properties with homeowners associations need HOA approval. Each additional approval body adds time to your timeline, often four to six weeks per review.

Don’t start construction before permits are approved. Starting without permits risks stop-work orders, fines, and mandatory removal of completed work. Worse, future buyers may struggle to get financing if renovations lack proper permits. The two to twelve weeks waiting for permits feels frustrating, but this timing is built into realistic renovation timelines.

Phase 3: Pre-Construction Preparation Timeline (2-3 Weeks)

The two to three weeks immediately before construction begins are critical for ensuring a smooth start. This pre-construction phase involves final preparations, material deliveries, site setup, and establishing communication protocols with your contractor.

Use the first week for final material ordering and delivery coordination. Your contractor provides a list of items needed before or during early construction phases. Order these materials with delivery scheduled for just before they’re needed. Ordering too early means storing materials, paying storage fees, or risking damage. Ordering too late delays construction while contractors wait for deliveries.

This week also involves preparing your home for construction chaos. Remove all furniture, decorative items, and personal belongings from renovation areas. Take down artwork, window treatments, and anything fragile. If staying in your home during renovation, establish barriers between construction zones and living spaces. Set up temporary kitchens or bathrooms if necessary. Create designated pathways for contractors to move materials and equipment without disrupting your daily life.

Week two focuses on utility disconnections and protection measures. Your contractor coordinates shutting off water, gas, or electrical service to renovation areas. They install protective coverings on floors and surfaces that aren’t being renovated. Set up construction dumpsters or waste removal systems. Notify neighbors about upcoming construction, estimated duration, and any potential disruptions. This courtesy prevents neighbor conflicts that could complicate your project.

During this pre-construction period, establish clear communication protocols with your contractor. How often will you receive progress updates? What’s the best method and time for questions? How quickly do you need to respond to decision requests? Who’s your primary contractor contact? Agreeing on these protocols now prevents miscommunication that causes delays later. For more details on managing contractor relationships, see our guide on hiring and working with contractors.

The final days before construction begins should include a pre-construction meeting with your contractor and all key subcontractors. Walk through the project together, review the timeline, clarify any remaining questions, confirm material delivery schedules, and verify everyone understands the scope. This meeting ensures everyone starts on the same page, reducing the risk of false starts or confusion that wastes time.

Phase 4: Construction Phase Timeline Breakdown

The construction phase represents the heart of your renovation timeline. Understanding how long each construction activity typically takes and how these activities sequence allows you to create realistic schedules. Construction phases must occur in specific order due to physical dependencies—you can’t finish walls before running electrical wiring inside them.

Demolition typically takes one to three weeks depending on project scope. Simple demolition—removing cabinets, countertops, and old fixtures—might complete in just days. Extensive demolition involving wall removal, multiple room gutting, or old system extraction takes longer. Demolition also includes hauling away debris, which requires dumpster coordination. For large projects, plan for a second dumpster midway through construction for ongoing waste removal.

Rough-in work for electrical, plumbing, and HVAC spans two to four weeks for most projects. This phase includes installing or relocating water supply lines, drain pipes, electrical wiring, HVAC ductwork, and any structural modifications needed for these systems. Rough-in must be completed and inspected before walls close up. Inspection scheduling can add several days to this phase, so request inspections early. Failed inspections require corrections and re-inspection, potentially adding a full week to your timeline.

Framing modifications and insulation take one to two weeks. If you’re not changing room layouts significantly, framing goes quickly. Major structural changes—removing bearing walls, creating new openings, or adding spaces—extend this phase. Once framing passes inspection, insulation gets installed before drywall.

Drywall installation, taping, mudding, and finishing require two to three weeks. This surprises many homeowners because drywall seems simple. However, proper drywall finishing requires multiple coats of joint compound with drying time between applications. Rushing drywall creates visible seams and imperfections that ruin your final results. Weather affects drying times—humid conditions extend this phase by days.

Painting takes one to two weeks depending on your home’s size and paint complexity. Simple one-color paint jobs move quickly. Multiple colors, accent walls, or special finishes take longer. Quality paint application requires primer coats, multiple finish coats, proper drying time between coats, and careful edge work. Attempting to speed through painting results in poor coverage, visible brush marks, and early paint failure.

Flooring installation spans one to three weeks based on material type and square footage. Luxury vinyl plank or laminate installs relatively quickly. Hardwood installation and finishing takes longer due to acclimation requirements, sanding, and finish application. Tile installation is time-intensive and requires curing time before grouting. Never rush flooring—improper installation causes squeaks, gaps, or premature wear.

Cabinet and countertop installation takes two to four weeks. Cabinet installation itself may only take days, but countertop templating, fabrication, and installation extends this timeline. Natural stone countertops require on-site templating after cabinets install, then fabrication takes one to two weeks, followed by installation. Time this phase carefully to prevent contractor downtime.

Final fixtures, trim, and finishing work need one to two weeks. This includes installing light fixtures, plumbing fixtures, door hardware, baseboards, crown molding, and any other finishing touches. While individually quick, these numerous small tasks add up to significant time.

Phase 5: Inspection and Approval Timeline (1-2 Weeks)

Inspections punctuate your construction timeline at multiple points, and understanding inspection requirements prevents unexpected delays. Most renovations require several inspections throughout construction plus a final inspection before you can legally occupy the renovated space.

Rough-in inspections typically occur after electrical, plumbing, and HVAC installation but before walls close up. This allows inspectors to verify systems are installed correctly and meet code. Schedule rough-in inspections as soon as your contractor completes this work—don’t wait. Most building departments require one to three business days’ notice for inspection scheduling, and inspectors may not visit for several days after your request. This can easily add five to seven days to your timeline.

Frame inspections verify structural modifications meet engineering requirements and code. If you’re removing walls, adding headers, or making significant structural changes, frame inspections occur after these modifications complete but before insulation and drywall installation. Like rough-in inspections, schedule these immediately when ready.

Failed inspections create significant delays. The inspector identifies code violations or installation problems. Your contractor must correct these issues, which takes hours to days depending on severity. Then you must schedule a re-inspection, adding another five to seven days. Prevent failed inspections by working with experienced contractors who understand local codes thoroughly.

Final inspections occur after all construction completes. The inspector verifies everything works properly, meets code, matches approved plans, and is safe for occupancy. You cannot legally occupy renovated spaces without passing final inspection. Some municipalities also require additional inspections like energy compliance verification or fire safety inspection for certain renovation types.

Build inspection timing into your construction timeline from the start. Add one week for each required inspection phase to account for scheduling delays and potential re-inspections. This buffer prevents inspection delays from derailing your overall timeline. Your contractor should proactively schedule inspections rather than waiting until work stops, keeping momentum going.

Phase 6: Final Cleaning and Punch List Timeline (1-2 Weeks)

The final phase of your renovation timeline addresses cleaning, completing punch list items, and final preparations before you move back in. Many homeowners underestimate how long this phase takes, but skipping proper completion creates frustration and unfinished details that linger for months.

Construction creates tremendous mess—dust, debris, scrap materials, and dirt accumulate throughout your home. Plan one full day for your contractor’s cleanup crew to perform initial cleaning. This includes removing all construction materials, disposing of final debris, vacuuming dust, wiping surfaces, and performing basic cleaning of renovated areas. Some contractors include this cleanup in their services, others charge separately. Clarify this in your contract.

After contractor cleaning, schedule professional deep cleaning before moving belongings back. Professional cleaners handle construction dust that settles in unexpected places—inside cabinets, on top of door frames, in HVAC vents. They clean windows, sanitize surfaces, and make your renovated space truly move-in ready. Budget one to two days for professional cleaning depending on renovation size.

The punch list identifies any incomplete or unsatisfactory items requiring contractor attention. Walk through your renovation systematically with your contractor, noting every issue—paint touch-ups needed, cabinet doors that don’t close properly, fixtures not working correctly, trim pieces missing, or anything not meeting your expectations. Document these items with photos and descriptions. Completing punch list items typically takes three to seven days depending on the list length and severity of issues.

Use this final phase to verify you’ve received all warranties, owner’s manuals, and product documentation for installed systems and appliances. Confirm your contractor has submitted all required documentation to your municipality for final permit closure. Request copies of all permits and inspection certificates for your home records—you’ll need these when selling.

Don’t release final payment until the punch list is completely resolved and you’ve verified everything works properly. Most contracts hold back ten to fifteen percent of the total cost until final completion. This holdback provides leverage ensuring contractors return to address any issues promptly.

Critical Timeline Factors That Cause Delays

Even the most carefully planned renovation timelines encounter delays. Understanding common delay causes helps you build appropriate buffers and respond effectively when delays occur. Some delays you can control, others you cannot, but all impact your timeline.

Material availability causes frequent delays, especially for custom or specialty items. Custom cabinets typically require eight to twelve weeks from order to delivery. Specialty tile, unique fixtures, or custom-sized appliances may have similar or longer lead times. Supply chain disruptions—increasingly common in recent years—can extend these timeframes unpredictably. Order long-lead items as early as possible and maintain communication with suppliers about delivery dates. Our material selection guide provides lead time expectations for common renovation materials.

Weather significantly impacts renovation timelines for projects involving exterior work, roofing, foundation work, or any activity requiring open structures. Rain delays concrete work, extreme temperatures affect paint and adhesive curing, and snow makes many exterior tasks impossible. Build seasonal considerations into your timeline. Spring and fall typically offer the most predictable weather windows for renovation work.

Contractor scheduling conflicts create delays when your contractor overcommits or experiences delays on other projects. Prevent this by working with contractors who maintain realistic project loads and communicate proactively about scheduling. When interviewing contractors, ask about their current project load and how they handle scheduling conflicts. A contractor juggling too many projects simultaneously cannot give your renovation proper attention.

Hidden problems discovered during demolition frequently extend timelines. Water damage, mold, outdated wiring requiring full replacement, structural issues, asbestos, or lead paint all require remediation before construction continues. Some of these problems require specialized contractors, testing, and special handling procedures that add weeks to your timeline. Build contingency time specifically for unexpected discoveries—assume you’ll find at least one surprise problem.

Permit delays occur when building departments take longer than expected to approve plans or when your project requires additional documentation or plan revisions. While you can’t control bureaucracy, you can minimize permit delays by submitting complete, professional-quality applications and maintaining communication with building officials. If your project requires multiple approval bodies, the timeline extends with each additional review.

Homeowner decision delays create problems when you can’t make timely selections or approvals. When your contractor asks which paint color you prefer, responding within twenty-four hours keeps work moving. Taking a week to decide stops progress entirely. Prevent decision delays by making key selections during the planning phase and responding promptly to any questions during construction.

Creating Buffer Time That Actually Works

Buffer time protects your renovation timeline from inevitable delays without extending your schedule unreasonably. Most renovation planning guides recommend adding ten to twenty percent buffer time, but understanding how and where to apply buffers makes them actually effective.

Apply different buffer percentages to different phases based on delay likelihood. Predictable phases like demolition need minimal buffer—perhaps five to ten percent. Uncertain phases like permitting or custom material delivery need substantial buffer—twenty to thirty percent. This targeted approach provides protection where you need it most without bloating your entire timeline unnecessarily.

Build buffer between phases rather than padding individual phase durations. If drywall takes three weeks, don’t estimate four weeks. Instead, add a one-week buffer between drywall completion and painting start. This approach provides flexibility while keeping contractors accountable to realistic phase durations. It also creates natural break points for addressing any catch-up work needed.

Create a separate contingency phase in your timeline specifically for addressing unexpected discoveries. When you find that water damage requiring two weeks of remediation, your contingency phase absorbs this time without pushing your entire project back. Think of contingency time as insurance—you hope you don’t need it, but you’re protected if you do.

Communicate buffer time carefully with contractors. If you tell your contractor the project must finish by May 1st but you’ve secretly built a three-week buffer making June 1st acceptable, your contractor has no incentive to maintain momentum in April. Instead, share the target completion date but acknowledge that unforeseen issues might require timeline adjustments. This honesty maintains urgency while managing expectations realistically.

Monitor buffer consumption throughout your project. If you’re six weeks into construction and you’ve already consumed three weeks of buffer, you’re on track for timeline overrun. Identify what’s causing delays and address these issues promptly before they compound. Regular monitoring allows course corrections before delays become timeline disasters.

Coordinating Multiple Contractors on Your Timeline

Most renovations involve multiple contractors or trades working in sequence or simultaneously. Coordinating these various professionals is one of the most challenging timeline management aspects. Poor coordination causes downtime where contractors wait for others to finish, or conflicts where multiple trades try working in the same space simultaneously.

Your general contractor handles most coordination if you’re working with one. However, understanding coordination principles helps you monitor progress and identify potential conflicts early. If managing contractors yourself, these principles become critical for timeline success.

The critical path concept identifies which activities must complete before others can start. In renovation timelines, certain activities form a critical path where delays directly push back your completion date. Other activities have flexibility—if they take a few extra days, other work continues unaffected. Map your critical path during planning. Focus your monitoring and buffer application on critical path activities since these determine your actual completion date.

Overlap non-dependent activities when possible to compress your timeline. While drywall mudding dries in your addition, your flooring contractor can work in an existing room receiving new floors. While waiting for custom cabinets to arrive, painters can complete other rooms. Identify these overlap opportunities during planning and coordinate contractors to maximize efficiency.

Prevent trade conflicts by establishing clear work zones and schedules. Multiple contractors cannot work in the same small space simultaneously. Create a detailed schedule showing which trades work where and when. Share this schedule with all contractors so everyone understands when they have access to different areas. Update the schedule regularly as work progresses or delays occur.

Maintain regular communication with all contractors about progress and upcoming work. Weekly coordination meetings—even brief phone calls—keep everyone informed about schedule changes, completed work, and next steps. These meetings prevent surprises where a contractor arrives expecting to work but cannot because prerequisite work isn’t complete.

Build handoff protocols between trades. When the electrician completes rough-in, what exactly must they do to signal the insulation contractor can begin? Creating clear handoff requirements prevents confusion and prevents the “I thought they were done” delays that waste days.

Timeline Adjustments: When and How to Modify Your Plan

No renovation timeline survives contact with reality unchanged. Successful renovation management requires knowing when to adjust your timeline and how to make adjustments that minimize disruption to the overall schedule.

Recognize when timeline adjustments become necessary rather than wishfully hoping you’ll catch up. If your contractor is consistently running three days behind schedule on every phase, you won’t magically catch up in later phases. Early recognition allows proactive adjustment before delays compound into crisis.

Some delays justify timeline extensions, others don’t. Legitimate extension reasons include permit delays beyond your control, weather that prevents critical work, material delivery delays for items with documented lead times, unexpected problems requiring remediation, or design changes you request mid-project. Poor contractor time management, preventable coordination failures, or your own decision delays don’t justify timeline extensions—these represent execution failures that need correction, not accommodation.

When adjusting timelines, communicate changes to all stakeholders immediately. Your contractor, all subcontractors, material suppliers with scheduled deliveries, inspectors with scheduled visits, and your own family all need updated timeline information. Delayed communication creates cascading problems as people operate on outdated schedules.

Evaluate timeline adjustment costs before approving extensions. Some delays don’t add direct costs—if work takes a week longer but stays within contractor’s fixed price, you’re only out time. Other delays carry substantial costs—extended temporary housing, storage fees, rushed delivery charges, or premium pricing for compressed schedules. Understanding cost implications helps you make informed decisions about whether to accept delays or invest in acceleration.

Consider acceleration options when delays threaten critical deadlines. Adding workers, extending work hours, or paying premium prices for faster material delivery can compress timelines when necessary. These approaches cost more but may be worthwhile if meeting your deadline prevents greater costs or disruptions. However, excessive acceleration often sacrifices quality—there’s a limit to how much you can speed work without compromising results. For more information on managing renovation challenges, read our article on handling renovation problems and changes.

Tools and Templates for Timeline Planning

Creating and managing your renovation timeline becomes significantly easier with the right tools. While complex project management software works for some, most homeowners succeed with simpler approaches that balance comprehensiveness with usability.

Spreadsheet-based timelines work well for straightforward renovations. Create a spreadsheet listing every phase and activity in rows, with columns for estimated start date, estimated duration, actual start date, actual duration, responsible contractor, and status. This simple format provides all essential information in one view and updates easily as work progresses. Most people already know how to use spreadsheets, eliminating learning curves.

Gantt chart software provides visual timeline representation showing phases, dependencies, and critical path. Software like Microsoft Project, Smartsheet, or free alternatives like GanttProject create professional-looking timelines that clearly communicate schedule information. These tools automatically adjust dependent activities when earlier phases change, maintaining schedule integrity. The visual format also helps identify overlapping phases and coordination opportunities.

Project management apps designed specifically for home renovations offer user-friendly interfaces without overwhelming complexity. Apps like BuildBook, Houzz Pro, or CoConstruct provide timeline features plus cost tracking, document storage, and communication tools in one platform. Many contractors already use these platforms, simplifying coordination if you adopt the same system.

Simple calendar applications work for smaller renovations. Block out phases on Google Calendar, Outlook Calendar, or similar tools. Set reminders for critical deadlines, material ordering dates, and inspection scheduling. Calendar approaches lack sophisticated dependency tracking but offer simplicity that prevents abandoning timeline management when other tools become overwhelming.

Regardless of tool choice, update your timeline weekly at minimum. Document actual completion dates for finished phases, adjust future phases based on current progress, note any delays and their causes, and communicate timeline status to your contractor and family. Regular updates keep your timeline relevant and useful throughout the project rather than becoming an ignored document gathering dust.

Conclusion: Your Roadmap to Renovation Timeline Success

Planning your home renovation timeline transforms overwhelming complexity into manageable phases with clear expectations. By understanding realistic duration estimates for each phase, recognizing common delay causes, building appropriate buffers, coordinating contractors effectively, and maintaining flexible but disciplined timeline management, you position your renovation for success.

Remember that your timeline planning begins six to twelve months before construction through careful pre-planning, designer selection, and contractor hiring. Construction itself follows a strict sequence from demolition through rough-in, finishing, and final inspections. Building appropriate buffer time—particularly between phases and for unexpected discoveries—protects your schedule without sacrificing accountability. Regular monitoring and prompt adjustments keep your timeline relevant as reality inevitably diverges from initial plans.

Your renovation timeline isn’t just a schedule—it’s a communication tool, a coordination framework, and a reality check that keeps expectations aligned with actual renovation requirements. Start with the frameworks in this guide, adapt them to your specific project, and maintain disciplined tracking throughout your renovation.

Ready to begin planning your renovation timeline? Start by reviewing our complete home renovation guide for comprehensive project planning strategies. Then explore our detailed articles on renovation budgeting, contractor selection, and managing construction phases to build the complete knowledge foundation for your successful renovation.